Reporter/Multimedia Journalist
The planned detonation of lead azide near Middletown, Iowa, Wednesday morning has centered on one major concern: lead dust that could travel beyond the Iowa Army Ammunition Plant.
But lead may not be the only substance released. Experts weigh in on what they worry could also be thrown across eastern Iowa, and how it could impact the people and environment there.
Possible byproducts, unanswered questions
Dr. Ron Sahu, a combustion engineer with about 35 years of environmental and air pollution experience, reviewed the permit materials and Army disclosures for a declaration filed in a lawsuit challenging the EPA permit.
Sahu said the permit identifies hydrochloric acid as a possible product of the detonation and refers more broadly to combustion byproducts. He said those byproducts could include formaldehyde, benzene and polycyclic aromatic hydrocarbons, or PAHs— compounds that can be toxic or carcinogenic to people.
Previous video in the playfinder above.
“None of those have been analyzed as to their impacts,” Sahu said.
At Tuesday’s briefing, Army officials focused on limiting lead particles. EPA Associate Administrator Tom Croci said federal teams would use mobile laboratories to detect “not only the air toxics, but anything that comes off the combustion.”
Army officials said the 68 drums contain lead azide in a water-and-ethanol mixture, with the explosive packed in burlap and sawdust. They said inspections in March found crystallized lead azide on the outside of the barrels, including on the lids and viewing ports.
ATF Director Robert Cekada said the ethanol mixture is intended to prevent freezing, but the magazines are not climate controlled and ethanol can evaporate over time. He said barrels were checked monthly and the mixture was checked and refilled annually, usually in September. Officials said they could not add more ethanol or open the barrels after crystals formed around the lids and bolts.
Cekada said opening a lid could detonate one barrel and set off others in the magazine. The Army said this is why it considers chemical neutralization and moving the barrels unsafe.
Sahu said a detonation involves rapid chemical reactions and energy release, but may not completely destroy all the material.
A broader issue: aging military munitions
Sahu said the challenge of aging military munitions is not new. He cited several sites where the military has dealt with aging chemical munitions:
- Umatilla, Oregon: The Army completed destruction of the chemical weapons stockpile stored at Umatilla Chemical Depot in 2011.
- Tooele, Utah: The Army completed its mission to destroy the Utah chemical weapons stockpile in 2012 at the Tooele Chemical Agent Disposal Facility.
- Pueblo, Colorado: The Army destroyed more than 780,000 chemical weapons stored at Pueblo Chemical Depot. The stockpile had been stored there since the 1950s; destruction was completed in 2023.
- Pine Bluff, Arkansas: The Army used the Pine Bluff Arsenal to destroy chemical warfare materiel recovered during environmental cleanup, including thousands of buried items dating to World War II.
He described a pattern of “long periods of inaction” followed by urgent decisions about disposal.
Army officials said the lead azide in Middletown was brought together from multiple locations in 2009. They said the material had been checked over the years, and that the current response began after crystallization was discovered in March. Acting Secretary of the Army Adam Telle said the Army has directed a review of its weapons storage facilities to help prevent a similar situation.
What else is stored nearby?
The Army permit application redacts portions of information about materials stored at the site. It’s unclear whether the redacted items would be removed before the detonation or destroyed with the lead azide.
Sahu says he’s also concerned about what is stored in other nearby magazines and how the blast’s energy could affect those items.
Army officials said the lead azide is stored in two earth-covered magazines. The briefing did not provide an inventory of materials in other nearby magazines. KCCI asked the Army whether any other materials would be removed or included in the detonation, and what could be released if they were destroyed. The Army had not responded by publication.
The Army scheduled the controlled detonation for about 9 a.m. Wednesday, Nov. 25, at the Iowa Army Ammunition Plant. It identified more than 9,700 pounds of lead azide planned for destruction. The Army said the material has degraded and become too sensitive to move or treat, and that a controlled, in-place detonation is safer than risking an uncontrolled explosion.
“At the very beginning, we wanted to prevent having to do a high-order detonation,” said Col. Aaron Teller, commander of the Army’s 71st Explosive Ordnance Disposal Group. “However, we were never able to find a viable alternative.”
Teller said the Army consulted with federal agencies and explosives manufacturers while evaluating other options.
What could show up on the landscape?
Scott Smith, an independent testing expert, said he and his team collected baseline samples in multiple directions around the plant before the detonation. The goal is to record what metals and other contaminants are already present, then compare those results with samples collected afterward.
He said his team plans to return after the detonation to collect additional samples. Lab results typically take three to five weeks, he said, though the team would try to speed up the process.
Smith also raised the possibility that substances could have combined effects.
“A single chemical, you may be safe, but a very small amount mixed in with another very small amount of another chemical creates what we call this synergistic effect,” he said.
Sahu said precipitation could also cause some airborne byproducts to settle.
He said many of the gases he raised concerns about would dissipate after several hours, but rain or snow could wash those substances out of the air and deposit them on the landscape.
Army describes containment and monitoring plans
At a Tuesday briefing, Army officials said they had added measures intended to limit the blast’s effects and keep particles from traveling beyond the plant.
Those measures include earthen barriers around the two magazines, two rows of 16,000-gallon water tanks, a water wall, foam, gel blocks and a tarp and containment screen over the magazines. The Army also plans to wet the surrounding ground and direct the blast through a vent toward an uninhabited area of the plant.
“Our goal is to get to zero release of lead particulate into the atmosphere,” said Col. Aaron Teller, commander of the Army’s 71st Explosive Ordnance Disposal Group.
Teller cited a 1977 Colorado detonation of about 7,000 pounds of lead azide, which he said had no mitigation. He said about 75% of the lead particulate stayed at the site and 25% entered the atmosphere. The Army believes its current measures can significantly reduce the amount that becomes airborne, but did not give a specific estimate for the reduction.
Army officials said they are updating their lead-dispersion models as weather forecasts change. They said the earlier maps showed an unmitigated scenario, while newer models account for the planned barriers and other safeguards. Officials emphasized that the maps are forecasts; measurements taken during and after the detonation will provide more information about what happened.
EPA Associate Administrator Tom Croci said teams would take samples before the detonation, monitor air during it and sample afterward. He said more than 150 teams would work across three states, with mobile labs to detect air toxics and “anything that comes off the combustion.” Croci said residents could request samples of their homes, property or schools, and that monitoring and public updates would continue as long as needed.
The Army’s latest guidance recommends that Middletown residents and people in an area extending five miles southwest of the plant to evacuate. Officials say they expect the detonation to produce lead dust, noise and vibration.